Construction / CONSTRUCTION OF NEW DRAINAGE SYSTEM AT THRESHOLD 15 OF MAFIA AIRPORT
Client
:
Millennium Challenge Account-Tanzania (MCA-T)
Location
:
Mafia Island, Tanzania
Schedule
:
2014 - 2015
Role
:
Prime Contractor
Details
:

Kuanta has provided all necessary personnel, materials, equipment and services to design, supply, deliver, install a new  drainage system at TH 15 side of Mafia Airport, Tanzania.

The road to the north of the runway bordered the RESA at threshold 15, close to a cliff. The old discharge across the road was washed away in April 2014 during a high intensity rain. The slope failure was 15-20 m wide and a portion of the road was lost. The scope of this mandate is as follows:

·          Diverting of site drainage to the beach with two new drainage routes A and B,

·          Permanent closing of existing culverts crossing the road,

·          Installation of 1,2m diameter concrete culverts including cut-off walls and supporting concrete slab,

·          Installation of 1.2m concrete and glass fiber pipes along the new routes,

·          Construction of new manholes,

·          Construction of outfall structures at the discharge locations on the beach,

·          Slope stabilization along the new drainage line,

·          Road reinstatement.

Within the scope of the project, below construction works have been executed by Kuanta machinery and personnel.

Supply all necessary equipment, material and personnel to: 

-       Excavation of trench at varying depths of 5040 cubic meters,

-       Backfilling and compaction of 4334 cubic meters original ground,

-       Construct 218 linear meters of security fencing,

-       Site clearance of 1008 cubic meters,

-       336 linear meters of 1200mm diameter concrete pipe laying,

-       117 linear meters of 1200mm diameter Fiber Reinforced Pipe laying,

-       1278 linear meters of water proofing around pipes,

-       1052 square meters of erosion control with geogrid and geotextile,

-       1442 square meters of erosion control with vegetation,

-        3694 cubic meters of excavation for manhole and stilling basin construction,

-        1601 square meters of formwork for manhole and stilling basin construction,

-        193 cubic meter of plum in concrete

-        Construction of 13 ea. manholes